kVA to Amps Calculator: Single-Phase & Three-Phase Conversion (2026)

PES Supply, a PES Global Group Company
· 11 min read PES Engineering Desk — reviewed by a licensed master electrician

Table of Contents

    kVA to Amps: Calculator & Conversion Guide

    Single-phase and three-phase full-load current at any voltage — with NEC breaker sizing built in.

    kVA-to-amps is the conversion behind nearly every transformer, generator, and commercial inverter specification. Unlike our kVA-to-kW guide — which is about power factor — this conversion ignores power factor entirely, because kVA already includes it. What you need instead is voltage. Enter kVA and volts in the calculator below and get full-load amps instantly, for both single-phase and three-phase systems.

    ⚡ kVA to Amps Calculator

    Single-phase or three-phase — pick your system voltage and get full-load amps instantly, plus the NEC 240.6 breaker it points to.

    Formula (1φ): A = kVA × 1,000 ÷ V  ·  Formula (3φ): A = kVA × 1,000 ÷ (√3 × VLL)

    Three-phase volts are line-to-line. Breaker suggestion = NEC 125% continuous rule rounded to the next standard rating (NEC 240.6). Instant results as you type.

    The kVA to Amps Formulas

    Apparent power S (in VA) equals voltage times current. Solve for current and scale kVA up by 1,000:

    Single-phase: A = kVA × 1,000 ÷ V
    Three-phase: A = kVA × 1,000 ÷ (√3 × VLL)

    The √3 (≈1.732) in the three-phase formula accounts for the 120° phase displacement between the three conductors: in a balanced three-phase system the total power is √3 × VLL × I, not 3 × V × I. Use line-to-line voltage — 208, 480, or 600 V — in that formula. If your nameplate shows line-to-neutral voltage (120, 277, 347 V), the equivalent form is A = kVA × 1,000 ÷ (3 × VLN), which returns the same per-phase amps.

    The inverse conversion — amps to kVA — is the same algebra reversed: kVA = A × V ÷ 1,000 (single-phase) or kVA = A × V × 1.732 ÷ 1,000 (three-phase). And if you need the watts side of the story, that requires power factor: kW = kVA × PF, covered step-by-step in our kVA-to-kW conversion guide.

    kVA to Amps Chart — Single-Phase

    kVA 120 V 208 V 240 V 277 V 480 V 600 V
    1 kVA 8.3 A 4.8 A 4.2 A 3.6 A 2.1 A 1.7 A
    5 kVA 41.7 A 24.0 A 20.8 A 18.1 A 10.4 A 8.3 A
    10 kVA 83.3 A 48.1 A 41.7 A 36.1 A 20.8 A 16.7 A
    15 kVA 125 A 72.1 A 62.5 A 54.2 A 31.3 A 25 A
    25 kVA 208.3 A 120.2 A 104.2 A 90.3 A 52.1 A 41.7 A
    37.5 kVA 312.5 A 180.3 A 156.3 A 135.4 A 78.1 A 62.5 A
    50 kVA 416.7 A 240.4 A 208.3 A 180.5 A 104.2 A 83.3 A
    75 kVA 625 A 360.6 A 312.5 A 270.8 A 156.3 A 125 A
    100 kVA 833.3 A 480.8 A 416.7 A 361 A 208.3 A 166.7 A

    Table 1 — Single-phase full-load amps: A = kVA × 1,000 ÷ V.

    kVA to Amps Chart — Three-Phase

    kVA 208 V 3φ 240 V 3φ 480 V 3φ 600 V 3φ
    9 kVA 25.0 A 21.7 A 10.8 A 8.7 A
    15 kVA 41.6 A 36.1 A 18.0 A 14.4 A
    30 kVA 83.3 A 72.2 A 36.1 A 28.9 A
    45 kVA 124.9 A 108.3 A 54.1 A 43.3 A
    75 kVA 208.2 A 180.4 A 90.2 A 72.2 A
    112.5 kVA 312.3 A 270.6 A 135.3 A 108.3 A
    150 kVA 416.4 A 360.8 A 180.4 A 144.3 A
    225 kVA 624.6 A 541.3 A 270.6 A 216.5 A
    300 kVA 832.7 A 721.7 A 360.8 A 288.7 A
    500 kVA 1,387.9 A 1,202.8 A 601.4 A 481.1 A

    Table 2 — Three-phase full-load amps per phase: A = kVA × 1,000 ÷ (1.732 × V_LL). Rows use standard transformer sizes.

    Where This Conversion Runs the Job

    Transformers (NEC Article 450)

    Every dry-type transformer nameplate is denominated in kVA, and NEC 450.3 protection rules key off rated current — which you must compute from kVA and voltage. A 75 kVA, 480 V three-phase transformer carries 90.2 A full-load secondary current. That number drives the secondary breaker (125 A at 125%), the conductor size (at least 1/0 AWG copper at 75 °C before adjustments), and the fault-current calculations downstream. Standard dry-type sizes — 15, 30, 45, 75, 112.5, 150, 225, 300, 500 kVA — exist precisely so these amp values land on serviceable equipment.

    Generators

    Standby generators are specified in kVA because the alternator's thermal limit is set by current, not real power. A 100 kW / 125 kVA unit (0.8 PF) at 480 V three-phase delivers 150.3 A — that is the figure your transfer switch, feeders, and breaker must carry. Undersizing here is one of the most expensive field mistakes; our generator sizing guide walks the full load-side process.

    Commercial solar inverters

    String and central inverters in the 50–350 kW class carry kVA ratings (typically kVA = kW at unity PF, with headroom for reactive support per IEEE 1547). A 125 kVA inverter at 480 V three-phase outputs 150.3 A AC — the input to your interconnection study, AC combiner sizing, and NEC 705.12 busbar loading calculation. Pair this with our NEC 690 disconnect guide for the protection side.

    Worked Examples

    Example 1 — Single-phase transformer feeder

    • Transformer: 25 kVA, 240 V single-phase secondary.
    • Full-load amps: 25 × 1,000 ÷ 240 = 104.2 A.
    • Continuous sizing: 104.2 × 1.25 = 130.2 A → 150 A next standard (NEC 240.6) or 125 A with NEC 240.4(B) rounding rules — check conductor ampacity first.
    • Conductor: 1/0 AWG copper (150 A at 75 °C) covers the 125 A frame.

    Example 2 — Three-phase generator output

    • Generator: 200 kVA standby, 480 V three-phase.
    • Full-load amps: 200,000 ÷ (1.732 × 480) = 240.6 A.
    • Transfer switch: next standard frame above full load → 250–260 A class; see our 200–225 A and full transfer-switch lineup.

    Example 3 — Commercial inverter AC current

    • Inverter: 125 kVA, 480 V three-phase output.
    • AC current: 125,000 ÷ (1.732 × 480) = 150.3 A.
    • NEC 690.8 inverter output circuit: 125% continuous → 187.9 A → 200 A breaker, 3/0 copper at 75 °C.

    A field note on nameplate literacy

    Transformer and generator nameplates pack the inputs for this conversion into a few compact lines: kVA rating, primary and secondary voltages, phase, impedance (%Z), and frequency. The impedance percentage deserves a mention even though it does not enter the full-load conversion — it caps the available fault current, which is why a 75 kVA, 4%Z transformer at 208 V can only deliver about 5.2 kA into a bolted fault (208.2 A ÷ 0.04). Full-load amps tell you what the equipment carries; impedance-limited amps tell you what it can deliver into a short, and breaker interrupt ratings (AIC) are chosen against the latter.

    NEC Context

    • NEC 450.3 (Transformers): overcurrent protection is expressed as percentages of rated current — you must convert kVA to amps before the table means anything. Primary-only protection can reach 125% (with secondary protection) or up to 250% in supervised arrangements.
    • NEC 240.6 (Standard ratings): after the 125% continuous multiplier (210.20, 215.3), round up to 15, 20, 25, 30, 35, 40, 45, 50, 60, 70, 80, 90, 100, 110, 125, 150, 175, 200, 225, 250, 300, 350, 400 A and beyond. The calculator above does this step automatically.
    • NEC 220 (Load calculations): service and feeder loads are computed in VA; converting to amps at the service voltage is the final step before selecting service equipment.
    • NEC 445 / 702 (Generators, optional standby): generator feeders are sized from nameplate current — derived from kVA and voltage exactly as above.

    Once amps are known, conductor selection goes through the NEC 310.16 ampacity chart, and overcurrent devices through our breaker sizing guide.

    Standard transformer (kVA) 480 V 3φ full-load A 125% design Next standard OCPD
    15 18.0 A 22.6 A 25 A
    30 36.1 A 45.1 A 50 A
    45 54.1 A 67.7 A 70 A
    75 90.2 A 112.8 A 125 A
    112.5 135.3 A 169.2 A 175 A
    150 180.4 A 225.5 A 250 A
    225 270.6 A 338.3 A 350 A
    300 360.8 A 451.1 A 500 A
    500 601.4 A 751.8 A 800 A

    Table 3 — Standard three-phase dry-type transformers at 480 V: full-load amps, 125% design current, and the NEC 240.6 overcurrent device.

    Inverse Reference: Amps → kVA

    Full-load amps 240 V 1φ 480 V 3φ 600 V 3φ
    20 A 4.8 kVA 16.6 kVA 20.8 kVA
    50 A 12 kVA 41.6 kVA 52 kVA
    100 A 24 kVA 83.1 kVA 103.9 kVA
    150 A 36 kVA 124.7 kVA 155.9 kVA
    200 A 48 kVA 166.3 kVA 207.8 kVA
    400 A 96 kVA 332.6 kVA 415.7 kVA
    600 A 144 kVA 498.8 kVA 623.5 kVA
    800 A 192 kVA 665.1 kVA 831.4 kVA

    Table 4 — Running the formula backward: kVA = A × V ÷ 1,000 (1φ) or A × V × 1.732 ÷ 1,000 (3φ). Useful when a switchgear schedule lists amps but the transformer catalog lists kVA.

    Common Mistakes to Avoid

    ⚠ The five errors that burn kVA-to-amps conversions

    1. Forgetting √3 on three-phase. A 45 kVA load at 480 V is 54.1 A — not 93.8 A. Omitting 1.732 oversizes wire and breakers by 73%; using it on single-phase undersizes them.

    2. Mixing line-to-line and line-to-neutral voltage. The √3 formula needs line-to-line volts (208/480/600). Feeding it 277 V returns nonsense. Either use V_LL with √3, or V_LN with 3 — never cross them.

    3. Applying power factor twice. kVA already contains the reactive component. Converting kVA to amps requires no PF; that's only needed for kVA↔kW (see our kVA-to-kW guide).

    4. Sizing the breaker to the load instead of 125%. Continuous loads (3+ hours — which transformers and inverters usually are) require conductors and protection at 125% of full-load current. A 90.2 A transformer secondary on a 100 A breaker violates 210.20; it needs 125 A.

    5. Using the primary voltage to check the secondary. A 75 kVA, 480→208/120 V transformer draws 90.2 A on the 480 V side but delivers 208.2 A on the 208 V side. Protection and conductors on each side are sized from that side's voltage.

    kVA to Amps: FAQ

    How do you convert kVA to amps?

    Divide the kVA figure (times 1,000) by the system voltage. Single-phase: A = kVA × 1,000 ÷ V. Three-phase: A = kVA × 1,000 ÷ (1.732 × line-to-line voltage). For example, a 25 kVA load on a 240 V single-phase service draws 104.2 A; the same 25 kVA on a 480 V three-phase system draws only 30.1 A per phase.

    How many amps is 1 kVA?

    It depends entirely on voltage. At 120 V single-phase, 1 kVA is 8.33 A. At 240 V, 4.17 A. At 480 V three-phase, 1.2 A. kVA measures apparent power, so there is no voltage-independent answer — you must know the system voltage to convert.

    What is the difference between kVA and kW?

    kW is real power doing work; kVA is apparent power (real power plus reactive power). They are related by power factor: kW = kVA × PF. Generators and transformers are rated in kVA because their thermal limits depend on total current, not just the real-power component. Our kVA-to-kW guide covers the power-factor side of this in detail.

    Why are transformers and generators rated in kVA instead of kW?

    Because the limiting factor inside a transformer or generator is current through the windings, which creates heat regardless of the load's power factor. A purely reactive load draws real current while delivering zero kW, so kW ratings would hide the thermal stress. kVA captures the full current burden.

    Does the three-phase formula use line or phase voltage?

    Use line-to-line voltage (208, 480, 600 V) with the √3 factor: A = kVA × 1,000 ÷ (√3 × V_LL). If you only know line-to-neutral voltage (120, 277, 347 V), you can use A = kVA × 1,000 ÷ (3 × V_LN) — the results are identical because V_LL = √3 × V_LN.

    What size breaker do I need for a 75 kVA transformer at 480 V?

    Full-load secondary current is 75 × 1,000 ÷ (√3 × 480) = 90.2 A. Applying 125% for continuous duty gives 112.8 A, so the next standard size is 125 A (NEC 240.6). Primary protection follows NEC 450.3 — up to 125% or 250% depending on supervision and secondary protection arrangements.

    Related Guides & Calculators

    Sizing a transformer, generator, or commercial inverter? Get a quote from Portlandia Electric Supply — we stock commercial generators, transfer switches, and commercial inverters with full spec support.

    Need Help Sizing This?

    Our team can help you calculate loads, select the right equipment, and source everything from one PO.

    📞 (502) 790-0600

    Email Our Team
    Solar Panels Generators Batteries / ESS EV Chargers Circuit Breakers Charge Controllers

    One PO. One Invoice. Every Trade Covered.

    PES Supply is the distribution arm of PES Global Group — 50,000+ SKUs from 169 authorized brands, LTL freight shipping from Louisville, KY.

    Get a Quote
    Share: X f in @

    Related Articles

    Volts to Amps Conversion: How to Calculate Amps from Volt...

    Sep 04, 2026

    MWh to kWh Conversion: Megawatt-Hours to Kilowatt-Hours C...

    Sep 04, 2026

    Watts to Kilowatts Conversion: W to kW Calculator + Chart...

    Sep 04, 2026

    mA to Amps Conversion: Milliamps to Amps Calculator + Cha...

    Sep 04, 2026

    Wire Ampacity Calculator (NEC 310.16): Copper & Aluminum ...

    Sep 04, 2026

    Generator Sizing Calculator: Running + Starting Watts to ...

    Sep 04, 2026

    Solar Panel Sizing Calculator: How Many Panels Does Your ...

    Sep 04, 2026

    Battery Runtime Calculator: Ah to Hours With DoD & Invert...

    Sep 04, 2026

    Voltage Drop Calculator: NEC 3%/5% Rule, Formula & Wire S...

    Sep 04, 2026

    Off-Grid Battery Bank Sizing Calculator: kWh, Amp-Hours &...

    Sep 04, 2026

    Solar Payback Calculator: Payback Period & 25-Year Saving...

    Sep 04, 2026

    EV Charger Circuit Calculator: Breaker & Wire Size per NE...

    Sep 04, 2026

    Service Entrance Load Calculator: NEC 220 Standard Method...

    Sep 04, 2026

    Conduit Bending Calculator: Offset Multiplier & Shrinkage...

    Sep 04, 2026
    LADWP and Investor-Owned Utility RFPs - A Bidder's Guide for Electrical and Renewable Equipment Supply

    LADWP and Investor-Owned Utility RFPs - A Bidder's Guide ...

    Sep 01, 2026
    Federal Contractor Buy-American Electrical Requirements - FAR 52.225 Compliance for Electrical, Solar, and Grid Equipment

    Federal Contractor Buy-American Electrical Requirements -...

    Sep 01, 2026
    State Cooperative Purchasing Programs for Electrical Equipment - Sourcewell, OMNIA, TIPS, NASPO ValuePoint

    State Cooperative Purchasing Programs for Electrical Equi...

    Sep 01, 2026
    Federal Solar RFP Response Template Library - Section L/M Compliance, Past Performance, and Bid Package Structure

    Federal Solar RFP Response Template Library - Section L/M...

    Sep 01, 2026
    GSA Schedule Roadmap for Electrical and Solar Suppliers - Multiple Award Schedule Application, Award, and Task Order Workflow

    GSA Schedule Roadmap for Electrical and Solar Suppliers -...

    Sep 01, 2026
    BABA Compliance for Electrical and Solar Equipment - 2 CFR 184, the 55% Rule, and How to Source Compliant Product

    BABA Compliance for Electrical and Solar Equipment - 2 CF...

    Sep 01, 2026
    HVAC Contractor Pallet Freight and LTL Guide: Hazmat Routing, DOT Compliance, and Landed Cost Economics

    HVAC Contractor Pallet Freight and LTL Guide: Hazmat Rout...

    Sep 01, 2026
    Commercial HVAC Refrigerant Compliance for Facility Managers: 40 CFR Part 82, Leak Repair Thresholds, and Penalty Avoidance

    Commercial HVAC Refrigerant Compliance for Facility Manag...

    Sep 01, 2026
    HVAC Service Tools Brand Selector: Fieldpiece vs Testo vs Fluke Digital Manifolds, Gauges, and Leak Detectors

    HVAC Service Tools Brand Selector: Fieldpiece vs Testo vs...

    Sep 01, 2026
    Refrigerant Recovery Equipment Buying Guide: Bacharach vs CPS vs Fieldpiece vs Yellow Jacket vs Appion

    Refrigerant Recovery Equipment Buying Guide: Bacharach vs...

    Sep 01, 2026
    PES Refrigerant Subscription Program: Recurring Pallet Delivery for HVAC Contractors

    PES Refrigerant Subscription Program: Recurring Pallet De...

    Sep 01, 2026
    EPA 608 Certification Guide: Type I, II, III, and Universal Testing Paths for HVAC Contractors

    EPA 608 Certification Guide: Type I, II, III, and Univers...

    Sep 01, 2026
    R-454B Transition Guide for HVAC Contractors: 2025 AIM Act, R-410A Phasedown, and Equipment Retrofits

    R-454B Transition Guide for HVAC Contractors: 2025 AIM Ac...

    Sep 01, 2026
    HVAC Contractor Refrigerant Buying Guide: R-410A, R-134a, R-22 Bulk Pricing & Hazmat Shipping

    HVAC Contractor Refrigerant Buying Guide: R-410A, R-134a,...

    Sep 01, 2026
    EPA Section 608 certification exam types and passing scores chart — PES Supply

    EPA Section 608 Certification: Complete Study Guide (Type...

    Aug 30, 2026

    R-410A Phase-Down 2026: What HVAC Contractors Need to Know

    Aug 29, 2026
    N-Type vs TOPCon vs HJT Solar Panels: Which Technology Is Best in 2026?

    N-Type vs TOPCon vs HJT Solar Panels: Which Technology Is...

    Aug 26, 2026
    How Many Solar Panels Do I Need for 10,000 kWh Per Month? - The Complete 2026 Guide

    How Many Solar Panels Do I Need for 10,000 kWh Per Month?...

    Aug 26, 2026
    Solar + Battery Storage: The Complete 2026 Guide for Homeowners

    Solar + Battery Storage: The Complete 2026 Guide for Home...

    Aug 24, 2026
    Commercial rooftop solar panels at sunset with American flag — ITC safe harbor and commence-construction rules for 2026

    ITC Safe Harbor & Commence-Construction: What Solar Buyer...

    Aug 17, 2026
    Solar panel modules stacked at a U.S. port facility with customs documentation overlay, representing Section 232 tariff compliance for solar imports

    Section 232 Solar Tariffs & Minimum Import Prices: The De...

    Aug 14, 2026
    Close-up of an electrical breaker panel with a licensed electrician testing circuits with a multimeter

    How to Size Circuit Breakers: NEC 125% Rule (2026)

    Aug 12, 2026
    Container port at golden hour with crane lifting crated solar panels over the dock

    Solar Module Sourcing in 2026: Regional Costs, Tariff Sta...

    Aug 09, 2026
    Pallets of stacked solar modules in a bright distribution warehouse with forklift and conduit racks

    Module Prices Hit $0.34/W — So Why Did Your Commercial Qu...

    Aug 08, 2026
    Two installers finishing a residential rooftop solar installation at sunset

    The Safe Harbor Deadline Passed. Here's What Actually Hap...

    Aug 07, 2026
    Worker in cleanroom suit inspecting a silicon ingot at a solar polysilicon factory, shipping containers beyond the window

    Section 232 Polysilicon Tariffs Hit Solar: What August 20...

    Aug 06, 2026
    Technician's hands with clipboard and tablet inspecting a home standby generator, shallow depth of field

    Generac Generator Warranty Explained: 5, 7, and 10-Year E...

    Aug 03, 2026
    Residential standby generator installed beside a modern suburban home's electrical service panel at golden hour

    Whole Home Generator Sizing Guide 2026: How Many kW Do Yo...

    Aug 03, 2026
    Wall-mounted home battery storage unit installed in a garage beside a solar inverter

    Battery Storage Incentives by State: 2026 Rebate Programs...

    Jul 30, 2026
    Rows of solar panels in a distribution warehouse, tied to 2026 supply and pricing trends

    Solar Market Outlook H2 2026: Panel Prices, Supply Chain,...

    Jul 29, 2026
    Imported solar panels in shipping crates at a port, subject of 2026 tariff updates

    Solar Industry Tariff Updates: What Installers Need to Kn...

    Jul 27, 2026
    A city skyline at dusk with glowing windows and power transmission lines in the foreground

    Growing Electricity Demand: Why Energy Policy Reform Is M...

    Jul 24, 2026
    A technician installing a wall-mounted mini-split heat pump indoor unit in a bright modern living room

    Mini Split Installation Cost (2026): Equipment, Labor & E...

    Jul 23, 2026
    Solar panels elevated over green farmland with sheep grazing beneath

    Harnessing the Sun and Soil: How Agrivoltaics is Revoluti...

    Jul 21, 2026
    A showroom display of several brand-new black solar panel models angled on stands

    Newest Solar Panels in 2026: Latest Models from Leading U...

    Jul 18, 2026

    Get Price Drops & Product Releases

    Weekly digest for installers and project managers — price drops, new stock, NEC code updates.

    PES Supply, a PES Global Group Company